T1 - Risk management of bored piling construction on sandy soils with real-time cost control
AU - Mata, Pedro
AU - Silva, Paula F.
AU - Pinho, Fernando F. S.
N1 - info:eu-repo/grantAgreement/FCT/6817 - DCRRNI ID/UIDB%2F04625%2F2020/PT#
UIDP/GEO/04035/2020
PY - 2021/5/20
Y1 - 2021/5/20
N2 - In a global society, in which geotechnical projects are increasingly designed in a country other than the one where construction takes place, geotechnical risk management must be extended to cover infrastructure works, which are smaller than dams and tunnels, for example, since there is a significant impact on works budget imponderables. Therefore, a risk management methodology based on the likelihood of the occurrence of certain events and their economic consequences is proposed, which is applicable to bored piles (Kelly drilled) in coarse soils, easy to use, and simple to implement since the initial stage of construction. Of 12 case studies of construction works involving bored piles (Kelly drilled) carried out in Luanda (Angola), two selected examples involving the proposed risk methodology on sandy soil layers with interbedded clays are discussed. Subsequently, whether the overall foundation contract budget is affected by assessed risk is determined, and what influence it has on the budget in the light of mitigating factors and associated real costs. This method intended to encourage the adaptation of sustainable risk management in bored piles construction by the site project managers, involving risk analysis concurrently with budgetary review. Though the level of assessed technical risk may be acceptable, overall costs associated with the contract in question may not be acceptable.
AB - In a global society, in which geotechnical projects are increasingly designed in a country other than the one where construction takes place, geotechnical risk management must be extended to cover infrastructure works, which are smaller than dams and tunnels, for example, since there is a significant impact on works budget imponderables. Therefore, a risk management methodology based on the likelihood of the occurrence of certain events and their economic consequences is proposed, which is applicable to bored piles (Kelly drilled) in coarse soils, easy to use, and simple to implement since the initial stage of construction. Of 12 case studies of construction works involving bored piles (Kelly drilled) carried out in Luanda (Angola), two selected examples involving the proposed risk methodology on sandy soil layers with interbedded clays are discussed. Subsequently, whether the overall foundation contract budget is affected by assessed risk is determined, and what influence it has on the budget in the light of mitigating factors and associated real costs. This method intended to encourage the adaptation of sustainable risk management in bored piles construction by the site project managers, involving risk analysis concurrently with budgetary review. Though the level of assessed technical risk may be acceptable, overall costs associated with the contract in question may not be acceptable.
KW - Activity-based costing (ABC)
KW - Bored piling
KW - Construction stage
KW - Kelly drilled
KW - Risk management
KW - Sandy soils
UR - http://www.scopus.com/inward/record.url?scp=85107202057&partnerID=8YFLogxK
U2 - 10.3390/infrastructures6050077
DO - 10.3390/infrastructures6050077
M3 - Article
AN - SCOPUS:85107202057
SN - 2412-3811
VL - 6
SP - 1
JO - Infrastructures
JF - Infrastructures
IS - 5
M1 - 77
ER -